Skip to main content

Microsoft Community Contributor Award 2011


July 29th 2011- Friday
Hello EPM folks,

It was a Friday which as usual starts from Client calls & I don't get the time to check my personal emails but on this day, i started my day with my gmail account & checking my emails , full of forum reply & few from others. I noticed an email from "support@microsoftcommunitycontributor" & subject was "Your online community contributions have been recognized by Microsoft".
_____________________________________________________________________________________
Dear Amit,

Congratulations! We’re pleased to inform you that your contributions to Microsoft online technical communities have been recognized with the Microsoft Community Contributor Award.

The Microsoft Community Contributor Award is reserved for participants who have made notable contributions in Microsoft online community forums such as TechNet, MSDN and Answers. The value of these resources is greatly enhanced by participants like you, who voluntarily contribute your time and energy to improve the online community experience for others. ..................................................
_____________________________________________________________________________________________________

Thanks everyone for motivating me to contribute my 2 cents to EPM World.


Comments

Anil Kumar Pal said…
Intersting and beautiful blog lovely presentation thanks for sharing your views...microsoft office 2007 We24support tech team are available 24/7 for repairs on computers, printers, laptops, desktops. Our tech team taken to new heights with our technician’s knowledge and support.at 1-866-978-0799 microsoft office 2007 updates

Popular posts from this blog

Update Project level Multiline Text Custom Fields

What a beautilful weather & I was kinda enjoying but suddenly One of My coworker pinged me & asked me a question about the Project level custom fields (multiline Text) so while I explained him about the usage of this kind of field, thought to write down somthing which might help Project Server community :)

Text custom fields can be multiline up to 4000 bytes, for use in project detail pages (PDPs) and with workflows for demand management in Project Web App. Multiline text custom fields are not usable in Project Professional. so I added a Project level Multiline text field in my PDP & now I wanted to update this field in a given project from my PSI program.

Here is the code for the Console application :
1. You will need to add project web service (ProjectWebSvc) web ref in the solution: http://servername/pwa/_vti_bin/PSI/Project.asmx?wsdl
2. Its very basic code, which has TEXT_VALUE update for a Multiline field
__________________________________________________________________…

Microsoft Project Server and SharePoint Server 2007 and 2010 June 2012 CU

The latest Cumulative Updates (CU) for Project and Project Server 2010 and 2007 have been released.  Feel free to open a support case if you have any questions around this or need assistance getting these patches deployed.
Feel free to join us in July for a TechNet webcast to go over these patches in greater detail.  The information for this event is below:
TechNet Webcast: Information About Microsoft Project and Project Server Cumulative June Update (Level 200)
https://msevents.microsoft.com/CUI/EventDetail.aspx?culture=en-US&EventID=1032454430&CountryCode=US
Project and Project Server 2010
This include a number of fixes, so Microsoft strongly recommends that you test this in a test environment based on your production environment before putting this fix live in production.
There was an issue found with one of the other Office Server products which needed to be addressed before release.  The issue has been fixed and the Server Rollup Packages are being rebuilt.  We expect the patch…

Project Server 2010 : bug with deliverables

if you create a new deliverable from Project site (site teamplate is customized..) using the grid row option (you can enter the deliverable name, start & finish), No deletion/update of columns in deviverables but other lists are custiomized. Once deliverable is crated a small message shows "Server is processing the changes to this row". (First screenshot) ANother way to create a new deliverable using the "New Item" form. so I created one more using this option. (Second screenshot) Now, I have two deliverables (D1 & D2) . When I open the MS project, I can see only one (D1) which is created via adding record using row option.(see the last screenshot). So Issue seems to be with the New Item form which doesn't sync the data to server. Looks liks a bug to me.